ABSTRACT
Quality electricity
supply in Nigeria is yet to be enjoyed by all due to certain technical and
non-technical factors. It is important to note that every power system consists
of various expensive equipment which need to be protected from dangerous fault
currents. A properly coordinated power system protection is that which isolates
only the faulted part of the network. For proper coordination, there should be
a time delay between the primary and secondary protection system. This time gap
between primary and secondary protection is known as Coordination Time Interval
(CTI). The
data for the modeling and simulation of overcurrent relay coordination for a typical
132/33 kV transmission station is gotten from the Umuahia 132/33 kV substation
of the Transmission Company of Nigeria (TCN). The Electric Transient Analyzer
Program (ETAP 16.0) software was used for the modeling and analysis. A three-phase
short circuit test was conducted on the network at three different locations
namely: Afara 33 kV feeder, the 33 kV bus section and at the 132 kV bus. The overall
maximum peak short circuit current of 20.15 kA was recorded. Afterwards, a
detailed sequence of operation of the station’s
overcurrent relays was carried out at these locations for standard inverse
relay characteristics, very inverse relay characteristics and extremely inverse
relay characteristics. Results showed that for a fault injected at Afara 33 kV
feeder, relays R16 and R21’s, time current curve (TCC) for the standard inverse
relay setting, very inverse relay setting and extremely inverse relay setting
curves, indicated a fault current of 3.141 kA, 3.153 kA and 3.153 kA
respectively which lasted for 3.51 s, 3.48 s and 3.48 s on the network
respectively. Similarly, the results showed that for a fault injected on the 33
kV busbar, R16, R17, R18 and R19’s, time current curve (TCC) for the standard
inverse relay setting, very inverse relay setting and extremely inverse relay
setting curves, indicated a fault current of 7.746 kA which lasted for 3.57 s,
3.57 s and 3.28 s on the network respectively. Moreover, it was shown that when
a fault was injected at 132kV bus, R1 and R2’s, time current curves (TCC) for
the standard inverse relay setting, very inverse relay setting and extremely
inverse relay setting curves, indicated a fault current of 2.843 kA which lasted
for 3.25 s, 3.47 s and 3.48 s on the network respectively. Finally, it was seen that
it is best to use relays with the extreme inverse characteristics at points
closer to the source - as a faster trip time of 0.0952 s was recorded at the
132kV side, whereas the very inverse relay setting and standard inverse relay
setting characteristics should be used downstream, as trip times of 3.51 s and
1.9 s respectively were recorded at locations farther from the source.
-- (2023). Modelling And Simulation Of A Coordinated Power System Protection Using Overcurrent Relay. Repository.mouau.edu.ng: Retrieved Dec 04, 2024, from https://repository.mouau.edu.ng/work/view/modelling-and-simulation-of-a-coordinated-power-system-protection-using-overcurrent-relay-7-2
--. "Modelling And Simulation Of A Coordinated Power System Protection Using Overcurrent Relay" Repository.mouau.edu.ng. Repository.mouau.edu.ng, 20 Jun. 2023, https://repository.mouau.edu.ng/work/view/modelling-and-simulation-of-a-coordinated-power-system-protection-using-overcurrent-relay-7-2. Accessed 04 Dec. 2024.
--. "Modelling And Simulation Of A Coordinated Power System Protection Using Overcurrent Relay". Repository.mouau.edu.ng, Repository.mouau.edu.ng, 20 Jun. 2023. Web. 04 Dec. 2024. < https://repository.mouau.edu.ng/work/view/modelling-and-simulation-of-a-coordinated-power-system-protection-using-overcurrent-relay-7-2 >.
--. "Modelling And Simulation Of A Coordinated Power System Protection Using Overcurrent Relay" Repository.mouau.edu.ng (2023). Accessed 04 Dec. 2024. https://repository.mouau.edu.ng/work/view/modelling-and-simulation-of-a-coordinated-power-system-protection-using-overcurrent-relay-7-2