Computer–Aided Scaleup Process Integration, Economic Feasibility And Uncertainty Evaluation Of Bioclarified Water Recovery From Petroleum Waste Water
Subscribe to read and download this work.
ABSTRACT
This study presents ASPEN Base Case Simulation (ABCS), preliminary process design with filtration integration, techno-economics and uncertainty analysis of bioclarified water production from petroleum wastewater. ABCS, scale-up design and economics were performed using inherent design and costing algorithms in ASPEN Batch Process Developer (ABPD) V10. The process profitability indices such as Net Present Value (NPV), Internal Rate of Return (IRR), Return on Investment (ROI) and Payback Time (PBT) were evaluated in a user-defined developed Microsoft-excel version 2018. Predictive models for predicting and optimizing techno-economic parameters: return on investment (ROI), payback time (PBT) and production rate (PR) were achieved in RSM via Box-Behnken Design (BBD) technique of Design Expert V13. The regression models gave R2 values of 0.9984, 0.9920 and 0.8867 for return on investment, payback time and production rate respectively. Monte Carlo Simulation in Crystal Ball Oracle software was used to perform the profitability sensitivity and uncertainty analyses. The annual production target (600,000litres/year) scale-up simulation results gave batch size 406litre/batch, annual number of batches produced 1469batches/year. Base case capacity results showed that the total capital investment, NPV, IRR, ROI and PBT are $631485, $68932.18, 9%, 15.8% and 6.33yrs respectively. Sensitivity analysis shows that selling price has the highest contribution for both the NPV and the IRR respectively. The certainty of the base case model after 30000trials was 99.98% for NPV, 90.89% for IRR and 61.23% for production rate. This study showed that petroleum wastewater BFS scale-up design is feasible.
TABLE OF CONTENTS
Cover page
Title page i
Declaration ii
Certification iii
Dedication iv
Acknowledgements v
Table of contents vi
List of tables viii
List of figures ix
Abbreviations/Nomenclature xi
Abstract xiii
CHAPTER 1
INTRODUCTION
1.1 Background of study 1
1.2 Statement of problem 6
1.3 Aim of study 7
1.4 Objectives 7
1.5 Significance of the study 8
1.6 Scope of the study 8
CHAPTER 2
LITERATURE REVIEW
2.1 Petroleum wastewater 9
2.2 Petroleum wastewater characteristics 10
2.3 Petroleum wastewater treatment technologies 11
2.3.1 Physical treatment 12
2.3.2 Membrane 12
2.3.3 Coagulation/flocculation 15
2.3.4. Electro-coagulation 17
2.3.5. Adsorption 18
2.3.6. Physical-chemical treatment 19
2.3.7 Chemical treatment 19
2.3.8 Biological treatment 20
2.3.8.1 Aerobic biological processes 21
2.3.8.2 Anaerobic biological process 21
2.3.9 Aerated lagoons 22
2.3.10 Activated sludge process 22
2.3.11 Biofilm-based reactor 22
2.4 Filtration process integration 23
2.5 Techno-Economic Analysis 24
2.5.1 Techno-economic analysis of bioclarified water production 24
2.5.2 Process modelling and simulation 25
2.5.3 Response Surface Methodology (RSM) 26
2.5.4 Process economics, sensitivity and uncertainty analyses 27
2.6 Review of related works 29
2.7 Research gap 30
CHAPTER 3
MATERIALS AND METHOD
3.1 Aspen batch base case process simulation environment 31
3.2 Simulation procedures using aspen batch process developer 32
3.2.1 Mixing 33
3.2.2 Coagulation stage 33
3.2.3 Flocculation stage 33
3.2.4 Settling stage 34
3.2.5 Filtration stage 34
3.3 Base case process description and scale-up process design 34
3.4 Process economics and profitability evaluation 36
3.5 Techno‑economic modelling and optimization study 38
3.5.1 Optimization study methodology 42
3.6 Monte Carlo simulation uncertainty and sensitivity analyses 42
CHAPTER 4
RESULTS AND DISCUSSION
4.1 Process base case scale-up simulation and annual production design results 44
4.2 Process economics results 48
4.2.1 One-factor at a time (OFAT) profitability sensitivity analysis 50
4.2.2 Effect of discounted rate cumulative cash flow diagram 53
4.3 RSM techno‑economic model fitting 54
4.3.1: Effect of the cost factors on PBT 58
4.3.2: Effect of the cost factors on ROI 62
4.3.3: Effect of the cost factors on production rate 66
4.4: Bioclarified water production optimization studies 70
4.5: Profitability uncertainty and sensitivity results 73
CHAPTER 5
CONCLUSION AND RECOMMENDATIONS
5.1 Conclusion 79
5.2 Research recommendations 80
5.3 Contributions to knowledge 80
REFERENCES 81
APPENDIX 95
LIST OF TABLES
Table Title Page
3.1: Properties of independent variable selected for BBD method 30
3.2: The BBD experimental design 30
4.1: Stream balance of bio-clarified water production from petroleum wastewater46
4.2: Batch process design throughput parameters of bio-clarified water production47
4.3: Process base-case economic parameters of bioclarified water production
from PPW 50
4.4: The BBD experimental design matrix 56
4.5: Fit summary for the production of bioclarified water from petroleum
wastewater 57
4.6: ANOVA Results for PBT 60
4.7: ANOVA Results for ROI 64
4.8: ANOVA Results for Production rate 68
4.9: Optimization criteria for bioclarified water production 71
LIST OF FIGURES
Figure Title Page
3.1: Process flowsheet for bio-clarified water reclamation from PPW 26
4.1: Distribution of ASPEN-installed cost factors for total capital investment 49
4.2a: variation of the project total capital investment with profitability indices 52
4.2b: variation of the project annual production cost with profitability indices 52
4.2c: Effect of discount rate on PBT, NPV, ROI and IRR 53
4.3: Profitability evaluation of bio-clarified water production using cumulative cash
flow diagram 54
4.4: Design expert plot, predicted vs. actual plot for (a) PBT (b) ROI
(c) Production rate 57
4.5: Design expert plot; response surface 3D plot for PBT with: (a) AB (b) AC
(c) AD (d) AE (e) BC (f) BD (g) BE (h) CD (i) CE (j) DE 62
4.6: Design expert plot; response surface 3D plot for ROI with: (a) AB (b) AC
(c) AD (d) AE (e) BC (f) BD (g) BE (h) CD (i) CE (j) DE 66
4.7: Design expert plot; response surface 3D plot for Production rate with: (a) AB
(b) AC (c) AD (d) AE (e) BC (f) BD (g) BE (h) CD (i) CE (j) DE 70
4.8: Optimization results ramp for bioclarified water production. 72
4.9a: Contribution of input variable variation on NPV 74
4.9b: Contribution of input variable variation on IRR 74
4.9c: Contribution of input variable variation on production rate 75
4.10a: Uncertainty level (NPV) for bioclarified water production from PPW 77
4.10b: Uncertainty level (IRR) for bioclarified water production from PPW 78
4.10c: Uncertainty level (production rate) for bioclarified water production from PPW 78
NOMENCLATURE OF ABBREVIATIONS
ABPD - Aspen Batch Process Developer
ASDM - activated sludge digestion model
BAF - biological aerated filter
BBD - Box-Behnken Design
BFS - Biocoagulation-Flocculation-Sedimentation
BOD - Biochemical oxygen demand
BTEX - chemicals (benzene, toluene, ethylbenzene and xylene)
CAPD - Computer-Aided Process Design
CCFD - Cumulative Cash Flow Diagram
CF - Coagulation-Flocculation
CF–MBR - cross-flow membrane bioreactor
CFS - Coagulation-Flocculation-Sedimentation
COD - Carbon Oxygen Demand
COD - Chemical Oxygen Demand
DPC - Direct Production Cost
FCI - Fixed Capital Investment
HF-MBR - hollow-fiber membrane bioreactor
HRT - hydraulic retention times
IPC - Indirect Production Cost
IRR - Internal Rate of Return
IRR - internal rates of return
MAD - Mean Absolute Deviation
MAPE - Mean Absolute Percentage Error
MBR - membrane bioreactor
MF - microfiltration
MSE - Mean Square Error
NA - naphthenic acids
NF - Nanofiltration
NPV - Net Present Value
NPV - net present values
NTU - Nephelometric Turbidity unit
OCB - Oracle Crystal Ball
PAH - Poly-Aromatic, Phenol and Hydrocarbons
PBT - Payback Time
PBT - payback time
PC - Production Cost,
PPW - Petroleum Produced Water
PW - Produced Water
RMSE - Root Mean Square Error
RO - Reverse Osmosis
ROI - return on investment
RSM - Response Surface Methodology
SS - Suspended Solids
TCI - Total Capital Investment
TCI - Total Capital Investment
TDP - Total Dissolved particles
TEA - Techno-economic analysis
TMP - Trans-membrane pressure
TPDC - Total Plant Direct Cost
TPIC - Total Plant Indirect Cost
TSS - Total Suspended Solids
UF - Ultrafiltration
WC - Working Capital
LIST OF APPENDIX
APPENDIX I: Optimization solutions for bioclarified water production
APPENDIX II: Definition of terms
Reviews
No reviews yet.
APA
OSOH, K. A. (2023). Computer–Aided Scaleup Process Integration, Economic Feasibility And Uncertainty Evaluation Of Bioclarified Water Recovery From Petroleum Waste Water. Michael Okpara University of Agriculture. Retrieved June 7, 2026, from http://repository.mouau.edu.ng/works/computeraided-scaleup-process-integration-economic-feasibility-and-uncertainty-evaluation-of-bioclarified-water-recovery-from-petroleum-waste-water-7-2
MLA
OSOH, KUFRE AUGUSTINE. "Computer–Aided Scaleup Process Integration, Economic Feasibility And Uncertainty Evaluation Of Bioclarified Water Recovery From Petroleum Waste Water." Michael Okpara University of Agriculture, 7 Sep. 2023, http://repository.mouau.edu.ng/works/computeraided-scaleup-process-integration-economic-feasibility-and-uncertainty-evaluation-of-bioclarified-water-recovery-from-petroleum-waste-water-7-2. Accessed June 7, 2026.
Chicago
OSOH, KUFRE AUGUSTINE. "Computer–Aided Scaleup Process Integration, Economic Feasibility And Uncertainty Evaluation Of Bioclarified Water Recovery From Petroleum Waste Water." Michael Okpara University of Agriculture (2023). Accessed June 7, 2026. http://repository.mouau.edu.ng/works/computeraided-scaleup-process-integration-economic-feasibility-and-uncertainty-evaluation-of-bioclarified-water-recovery-from-petroleum-waste-water-7-2